Project Update
Building Dedication--The dedication service and open house will be Sunday, April
21. Mark your calendar and plan to join us on this very special
day of thanksgiving and celebration.
February Work--Since carpeting was completed on the 1st and 2nd
floors, and restrooms became fully operational, we've now taken
over use of these areas. The nurseries are in use and Paige Hackney,
our secretary, and Steve Wilson are enjoying working out of their
new offices (with windows!).
In the basement, finishing a handicapped-accessible
restroom and trimming of the fellowship room and hallway are
underway. Coat racks have been built and only await the necessary
hardware, on order, to be installed.
In the original building, the stained glass
windows were reinstalled, the back stairway was finished off
and interior basement storm windows and fireplace mantel were
built and installed.
|